Proposed Administrative Settlement Pursuant to the Comprehensive 
Environmental Response, Compensation and Liability Act (``CERCLA''), as 
Amended by the Superfund Amendments and Reauthorization Act--Idaho Pole 
Co. Site, Bozeman, MT

AGENCY: U.S. Environmental Protection Agency.

ACTION: Notice; request for public comment.

-----------------------------------------------------------------------

SUMMARY: In accordance with the requirements of section 122(i)(1) of 
the Comprehensive Environmental Response, Compensation, and Liability 
Act, as amended (``CERCLA''), 42 U.S.C. 9622(i)(1), notice is hereby 
given of a proposed administrative settlement under section 122(h) of 
CERCLA, 42 U.S.C. 9622(h) concerning the Idaho Pole Company site near 
Bozeman, Montana. The proposed administrative settlement requires Idaho 
Pole Company (Washington Corporation); Idaho Pole Company (Co-
Partnership); Burlington Northern Railroad Company; L.D. McFarland 
Company, Ltd.; McFarland Cascade Holdings, Inc.; Brendon Corry 
McFarland; and Gregory D. McFarland (``Settling Parties'') to pay 
$2,193,578.00 to the U.S. Environmental Protection Agency (``EPA''). 
The settlement resolves the liability of Settling Parties to the United 
States under Section 107 of CERCLA for reimbursement of response costs 
incurred at the Idaho Pole Company site pursuant to CERCLA through 
September 30, 1993.

DATES: Opportunity for comment: Comments must be submitted on or before 
March 31, 1994.

ADDRESSES: The proposed settlement is available for public inspection 
at the EPA Montana Office Record Center, Federal Building, 301 S. Park, 
Drawer 10096, Helena, Montana 59626-0096. Comments should be addressed 
to Jim Harris, Remedial Project Manager, at the above address, and 
should reference the Idaho Pole Company site.

FOR FURTHER INFORMATION CONTACT:
Jim Harris at (406) 449-5720.

It is so agreed:

    Dated: February 9, 1994.
William Yellowtail,
Regional Administrator.
[FR Doc. 94-4650 Filed 2-28-94; 8:45 am]