[Federal Register Volume 59, Number 208 (Friday, October 28, 1994)]
[Unknown Section]
[Page ]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 94-26705]


[Federal Register: October 28, 1994]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. ER95-28-000, et al.]


Pennsylvania Power & Light Co., et al.; Electric Rate and 
Corporate Regulation Filings

October 20, 1994.
    Take notice that the following filings have been made with the 
Commission:

1. Pennsylvania Power & Light Company

[Docket No. ER95-28-000]

    Take notice that on October 11, 1994, Pennsylvania Power & Light 
Company (PP&L), tendered for filing with the Federal Energy Regulatory 
Commission an Electrical Output Sales Agreement (Agreement) between 
PP&L and Allegheny Electric Cooperative, Inc. (Allegheny) dated 
September 23, 1994. The Agreement provides for the sale by PP&L to 
Allegheny of electrical output solely for Allegheny's use in wholesale 
bulk power transactions.
    PP&L has requested an effective date of October 12, 1994, for the 
Agreement. In accordance with 18 CFR 35.11, PP&L has requested waiver 
of the sixty day notice period in 18 CFR 35.2(e).
    PP&L states that a copy of its filing was provided to Allegheny and 
to the Pennsylvania Public Utility Commission.
    Comment date: November 3, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

2. Pennsylvania Power & Light Company

[Docket No. ER95-29-000]

    Take notice that on October 11, 1994, Pennsylvania Power & Light 
Company (PP&L), tendered for filing with the Federal Energy Regulatory 
Commission an Electrical Output Sales Agreement (Agreement) between 
PP&L and Consolidated Edison Company of New York, Inc. (Con Ed) dated 
August 22, 1994. The Agreement provides for the sale by PP&L to Con Ed 
of electrical output solely for Con Ed's use in wholesale bulk power 
transactions.
    PP&L has requested an effective date of October 12, 1994 for the 
Agreement. In accordance with 18 CFR 35.11, PP&L has requested waiver 
of the sixty-day notice requirement in 18 CFR 35.2(e).
    PP&L states that a copy of its filing was provided to Con Ed and to 
the Pennsylvania Public Utility Commission.
    Comment date: November 3, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

3. Pennsylvania Power & Light Company

[Docket No. ER95-30-000]

    Take notice that on October 11, 1994, Pennsylvania Power & Light 
Company (PP&L), tendered for filing with the Federal Energy Regulatory 
Commission an Electrical Output Sales Agreement (Agreement) between 
PP&L and Electric Clearinghouse, Inc. (ECI) dated August 31, 1994. The 
Agreement provides for the sale by PP&L to ECI of electrical output 
solely for ECI's use in wholesale bulk power transactions.
    PP&L has requested an effective date of October 12, 1994 for the 
Agreement. In accordance with 18 CFR 35.11, PP&L has requested waiver 
of the sixty-day notice requirement in 18 CFR 35.2(e).
    PP&L states that a copy of its filing was provided to ECI and to 
the Pennsylvania Public Utility Commission.
    Comment date: November 3, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

4. PSI Energy, Inc.

[Docket No. ER95-31-000]

    Take notice that on October 11, 1994, PSI Energy, Inc. (PSI), 
tendered for filing a First Supplement Agreement to the Interchange 
Agreement, dated January 29, 1993, between PSI and Blue Ridge Power 
Agency (Blue Ridge).
    The Supplemental Agreement revises Service Schedule F--Term 
Capacity and Energy. The Reserved Capacity changes the Mws per year, 
and updates language changes.
    PSI and Blue Ridge have requested an effective date of December 6, 
1994.
    Copies of the filing were served on Blue Ridge Power Agency, the 
Virginia State Corporation Commission and the Indiana Utility 
Regulatory Commission.
    Comment date: November 3, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

5. Maine Electric Power Company

[Docket No. ER95-32-000]

    Take notice that on October 11, 1994, Maine Electric Power Company 
(MEPCO), tendered for filing a Transmission Service Agreement between 
MEPCO and Central Maine Power Company (CMP), dated as of October 26, 
1994 (Agreement). MEPCO will provide CMP with firm transmission service 
over the MEPCO transmission system for the purpose of transmitting the 
output of the 32 megawatt (net) biomass electric generating plant 
located in the Town of Fort Fairfield, Maine, to be known as 
``Aroostock Valley Electric Company''. The rates for such service shall 
be as provided in MEPCO Rate Schedule FPC No. 1 on file with the 
Commission.
    Comment date: November 3, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

6. Portland General Electric Company

[Docket No. ER95-33-000]

    Take notice that on October 12, 1994, Portland General Electric 
Company (PGE), tendered for filing the 1994-1995 One Year Share-the-
Shortage Agreement (the Agreement), among the following parties: Idaho 
Power Company; The Montana Power Company; PacifiCorp; Portland General 
Electric Company; Puget Sound Power & Light Company; The Washington 
Water Power Company; Bonneville Power Administration; Public Utility 
District No. 1 of Chelan County; Public Utility District No. 1 of 
Cowlitz County; Public Utility District No. 1 of Douglas County; Public 
Utility District No. 2 of Grant County; Public Utility District No. 1 
of Pen Oreille County; The Eugene Water & Electric Board; City of 
Seattle acting by and through its City Light Department; City of Tacoma 
acting by and through its Public Utilities Department.
    PGE states that the Agreement relates to service for the purpose of 
alleviating energy shortages of one or more of the parties to the 
Agreement and to help ensure that all of the parties can meet their 
obligations to serve their respective retail customer loads. A copy of 
the filing was served upon the parties to the Agreement.
    Under the provisions of 18 CFR 35.11, the Parties request that the 
Commission grant waiver of the notice requirements of 18 CFR 35.3 to 
allow the Agreement to become effective December 1, 1994.
    Comment date: November 3, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

7. J. Aron & Company

[Docket No. ER95-34-000

    Take notice that on October 12, 1994, J. Aron & Company (J. Aron), 
tendered for filing pursuant to Rules 205 and 207 of the Commission's 
Rules of Practice and Procedure (18 CFR 385.205, 385.207 (1994)) its 
Rate Schedule No. 1, to be effective 60 days from and after October 12, 
1994, together with a petition for a clarification of various matters, 
and for certain waivers and blanket approvals under various regulations 
of the Commission.
    J. Aron intends to engage in electric power and energy transactions 
as a marketer. J. Aron's power marketing activities will include 
purchases of capacity, energy, and/or transmission services from 
electric utilities, qualifying facilities, and independent power 
producers. J. Aron will resell such power to other purchasers on an 
arms-length basis and at mutually agreed upon rates. J. Aron is not in 
the business of producing or transmitting electric power and does not 
have title to any electric power generation or transmission facilities.
    Comment date: November 3, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

8. Hermiston Generating Company, L.P.

[Docket No. ES95-6-000]

    Take notice that on October 18, 1994, Hermiston Generating Company, 
L.P. (Hermiston) filed an application under Section 204 of the Federal 
Power Act seeking authorization to assume obligations and liabilities 
in a maximum principal amount of $395 million for a maximum loan period 
of 20 years for the construction of a cogeneration project. The 
obligations and liabilities will be in the form of a credit facility 
that includes as components, (1) various loan facilities, a portion of 
which will be in the form of working capital facilities, and (2) letter 
of credit facilities. Hermiston requests exemption from the 
Commission's competitive bidding regulations pursuant to Section 
34.2(a)(ii). Also, Hermiston requests waiver of the requirements of 
Sections 34.2(b) and 34.3(n) to the extent necessary.
    Comment date: November 2, 1994, in accordance with Standard 
Paragraph E at the end of this notice.

Standard Paragraphs

    E. Any person desiring to be heard or to protest said filing should 
file a motion to intervene or protest with the Federal Energy 
Regulatory Commission, 825 North Capitol Street, N.E., Washington, D.C. 
20426, in accordance with Rules 211 and 214 of the Commission's Rules 
of Practice and Procedure (18 CFR 385.211 and 18 CFR 385.214). All such 
motions or protests should be filed on or before the comment date. 
Protests will be considered by the Commission in determining the 
appropriate action to be taken, but will not serve to make protestants 
parties to the proceeding. Any person wishing to become a party must 
file a motion to intervene. Copies of this filing are on file with the 
Commission and are available for public inspection.
Lois D. Cashell,
Secretary.
[FR Doc. 94-26705 Filed 10-27-94; 8:45 am]
BILLING CODE 6717-01-P