DEPARTMENT OF THE INTERIOR
Office of the Secretary
Section 4(e) Conditions for the Kerr Hydroelectric Project;
Montana
AGENCY: Department of the Interior.
ACTION: Notice of Availability; Request for Comment.
-----------------------------------------------------------------------
SUMMARY: The Department of the Interior, in compliance with the terms
of the Kerr Hydroelectric Project license, The Montana Power Company,
32 FERC 61,070 (1985), announces the availability of its proposed
Section 4(e) conditions for public review and comment. Pursuant to the
Federal Power Act, 16 U.S.C. 797(e), the proposed conditions provide
for the adequate protection and utilization of the Flathead Indian
Reservation and the Fish and Wildlife Service administered Flathead
Waterfowl Production Area.
DATES: Written comments regarding the Secretary's proposed Section 4(e)
conditions will be accepted until close of business on or before
December 22, 1994. All comments received will be considered in the
preparation of the Secretary's final Section 4(e) conditions for the
Kerr Hydroelectric Project.
ADDRESSES: Comments should be sent to Anne Crichton, Department of the
Interior, Office of the Solicitor, 1849 C Street, NW., Mail Stop 6456,
Washington, DC 20240.
FOR FURTHER INFORMATION CONTACT:
Janice Schneider, Department of the Interior, Office of the Solicitor,
1849 C Street, NW., Mail Stop 6456, Washington, DC 20240, 202-208-6967.
SUPPLEMENTARY INFORMATION: The Kerr Hydroelectric Project (``Project'')
is located on the Flathead Indian Reservation, and in Flathead and Lake
Counties, in northwestern Montana. The Kerr Dam and portions of the
project works, including approximately one half of the Project's
reservoir, are located within the exterior boundary of the Flathead
Indian Reservation. The north half of the Project's reservoir is
located in Flathead and Lake Counties. At the north shore of Flathead
Lake, a portion of the Project is located within the Flathead Waterfowl
Production Area, which is owned and administered by the Fish and
Wildlife Service as part of the National Wildlife Refuge System.
On July 17, 1985, as the result of a negotiated settlement, the
Federal Energy Regulatory Commission (``Commission'') issued a new 50-
year operating license for the Kerr Project, jointly to the Montana
Power Company and the Confederated Salish and Kootenai Tribes as co-
licensees. The Montana Power Company, 32 FERC 61,070 (1985). The
specific terms of the license provide, inter alia, that
[T]he Secretary [of the Interior] shall be allowed * * * to
impose such reasonable license conditions with respect to fish [and
wildlife] and related environmental concerns as the Secretary would
be empowered under Section 4(e) [of the Federal Power Act] to
require * * *.\1\
---------------------------------------------------------------------------
\1\Section 4(e) of the Federal Power Act (FPA) authorizes the
Commission to issue licenses for hydroelectric projects ``upon any
part of the public lands and reservations of the United States.''
FPA Section 4(e), 16 U.S.C. 797(e) (1988 & Supp. 1992). Such
licenses ``shall be subject to and contain such conditions as the
Secretary of the department under whose supervision such reservation
falls shall deem necessary for the adequate protection and
utilization of such reservation.'' Id. (emphasis added). The
mandatory language of Section 4(e) requires the Commission to
accept, without modification, Secretarial conditions reasonably
related to the protection and adequate utilization of the
reservation and its purposes, and which are supported by substantial
evidence. See Escondido Mutual Water Co. v. La Jolla Band of Mission
Indians, 466 U.S. 765, 777, n. 18, 778 (1983).
Articles 45(b) and 46(c).
The Kerr Project license requires that the Secretary provide for
``notice and opportunity for hearing'' in the formulation of the
Sec. 4(e) conditions for the Kerr Project. Id. Consistent with the
terms of the Kerr Project license, the Secretary is providing
interested parties with notice and an opportunity to comment on the
proposed Section 4(e) conditions.
The proposed conditions for the Flathead Indian Reservation provide
for the imposition of a base load operational scenario at the Kerr
Project. This operational scenario precludes the use of Kerr Dam as a
load regulating or peak power generation facility, and requires minimum
flows, certain restrictions on flow fluctuations (ramping rates), and a
two year ramping rate study. In addition, the proposed conditions
provide for non-operational measures designed to protect and provide
for adequate utilization of the Flathead Indian Reservation in
conjunction with operational measures. The non-operational measures
include the development of a Fish and Wildlife Implementation Strategy,
development of an operational rule curve, habitat acquisition, habitat
development, fishery supplementation and reintroduction, development of
recreational resources, and the identification and protection of
cultural resources on the Flathead Indian Reservation. The proposed
conditions for the Flathead WPA provide for the imposition of erosion
control on the north shore of Flathead Lake and the upper Flathead
River, island restoration, and habitat acquisition and development. The
costs of all measures will be borne by the project licensees.
The proposed conditions are available for review at the Department
of the Interior, 1849 C Street, NW., Washington, DC in room 6443.
Copies of the proposed Section 4(e) conditions are being sent to all
individuals, agencies and organizations on the Commission's service
list for the Kerr Project, and to those who have otherwise requested to
be included on the Secretary's Kerr Project Section 4(e) mailing list.
The document will be mailed to all interested parties requesting
copies. The Secretary's final conditions will be informed by evidence
and comments submitted within 30 days of the date of publication of
this notice.
Dated: November 16, 1994.
Willie R. Taylor,
Acting Director, Office of Environmental Policy and Compliance.
[FR Doc. 94-28737 Filed 11-21-94; 8:45 am]