[Federal Register Volume 63, Number 218 (Thursday, November 12, 1998)]
[Notices]
[Pages 63335-63336]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 98-30256]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-259]
Tennessee Valley Authority; Notice of Withdrawal of Application
for Amendment to Facility Operating License
The U.S. Nuclear Regulatory Commission (the Commission or NRC) has
granted a request by the Tennessee Valley Authority (TVA) to withdraw
its June 2, 1995, application for an amendment to Facility Operating
License DPR-33 issued to TVA for the operation of the Browns Ferry
Nuclear Plant, Unit 1, located in Limestone County, Alabama. The
application was revised by letter dated March 6, 1997, and was
supplemented by letters dated April 11, 1997, and March 13, 1998.
Notice of consideration of issuance of this amendment was published in
the Federal Register on August 16, 1995 (60 FR 42609). The application
also requested similar amendments to Facility Operating Licenses DPR-52
and DPR-68 for Browns Ferry Nuclear Plant, Units 2 and 3 respectively.
The requested actions for Units 2 and 3 have been approved.
The proposed amendment, submitted in custom Technical Specification
(TS) format, would have revised the custom TSs for Unit 1 to include
changes associated with the implementation of the Power Range Neutron
Monitor (PRNM) upgrade, and to incorporate changes related to the
implementation of Average Power Range Monitor (APRM) and Rod Block
Monitor technical specification improvements and Maximum Extended Load
Line Limit (MELLL) Analysis. A general revision to the application was
submitted on March 6, 1997, and parallel changes in Improved TS (ITS)
format were submitted on April 11, 1997, and revised by a submittal
dated March 13, 1998.
On July 14, 1998, NRC approved the conversion from custom TSs to
ITSs (Amendment No. 234) for Unit 1. On October 5, 1998, TVA informed
the staff by letter that because the custom TSs are no longer in use,
the Unit 1 TS changes previously proposed in custom format for PRNM/
MELLL are no longer needed. Also, because TVA has no firm schedule for
the restart of Unit 1, the PRNM/MELLL proposed changes in ITS format
also are being withdrawn. Furthermore, since TVA does not now have a
firm schedule for the restart of Unit 1, any changes associated with
the PRNM/MELLL will be resubmitted prior to Unit 1 restart.
For further details with respect to this action, see the
application for amendment dated June 2, 1995, and March 6, 1997, and
TVA's letters dated April 11, 1997, and March 13, 1998, which are
available for public inspection at the Commission's Public Document
Room, the Gelman Building, 2120 L Street, NW., Washington, DC and at
the local public document room located at the Athens Public Library,
405 E. South Street, Athens, Alabama.
Dated at Rockville, Maryland, this 4th day of November 1998.
[[Page 63336]]
For the Nuclear Regulatory Commission.
Albert W. De Agazio,
Senior Project Manager, Project Directorate II-3, Division of Reactor
Projects--I/II, Office of Nuclear Reactor Regulation.
[FR Doc. 98-30256 Filed 11-10-98; 8:45 am]
BILLING CODE 7590-01-P