NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-025 and 52-026; NRC-2008-0252]


Southern Nuclear Operating Company, Inc.; Vogtle Electric 
Generating Plant, Units 3 and 4 Inspections, Tests, Analyses, and 
Acceptance Criteria

AGENCY: Nuclear Regulatory Commission.

ACTION: Determination of the successful completion of inspections, 
tests, and analyses.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has 
determined that specified inspections, tests, and analyses have been 
successfully completed, and that specified acceptance criteria are met 
for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4.

DATES: Determinations of the successful completion of inspections, 
tests, and analyses for VEGP Units 3 and 4 are effective on the dates 
indicated in the NRC staff's verification evaluation forms for the 
inspections, tests, analyses, and acceptance criteria (ITAAC).

ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2008-0252. Address 
questions about Docket IDs in Regulations.gov to Stacy Schumann; 
telephone: 301-415-0624; email: [email protected]. For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced in this document (if that document is available in 
ADAMS) is provided the first time that a document is referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents, by appointment, at the NRC's PDR, Room P1 B35, One White 
Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. To make 
an appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 
8:00 a.m. and 4:00 p.m. (ET), Monday through Friday, except Federal 
holidays.

FOR FURTHER INFORMATION CONTACT: Cayetano Santos, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-7270, email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Licensee Notification of Completion of ITAAC

    Southern Nuclear Operating Company, Inc. Georgia Power Company, 
Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG Power SPVJ, 
LLC., MEAG Power SPVP, LLC., and the City of Dalton, Georgia, 
(hereafter called SNC or the licensee) has submitted ITAAC closure 
notifications (ICNs) under section 52.99(c)(1) of title 10 of the Code 
of Federal Regulations (10 CFR), informing the NRC that the licensee 
has successfully performed the required inspections, tests, and 
analyses, and that the acceptance criteria are met for:

VEGP Unit 3 ITAAC

    2.1.01.04 (4), 2.1.02.08b (30), 2.1.02.09a (41), 2.1.02.09b.ii 
(43),, 2.1.02.11a.ii (47), 2.1.02.12a.iv (56), 2.1.02.15 (67), 
2.1.03.07.i (78), 2.2.01.02a (91), 2.2.01.07.ii (108), 2.2.01.08 (109), 
2.2.01.11a.iii (116), 2.2.01.11b (118), 2.2.02.01 (119), 2.2.02.02a 
(120), 2.2.02.11a.i (154), 2.2.03.01 (158), 2.2.03.08b.01 (175), 
2.2.03.08c.vii (192), 2.2.03.08c.viii (193), 2.2.03.08c.ix (194), 
2.2.03.12a.i (214), 2.2.04.02a (220), 2.2.04.12a.i (248), 2.3.02.02a 
(285), 2.3.02.05.i (291), 2.3.03.03c (322), 2.3.03.04 (324), 
2.3.06.05a.i (361), 2.3.06.09b.ii (375), 2.3.07.02a (392), 2.3.07.07c 
(408), 2.3.10.05a.i (437), 2.3.13.02 (459), 2.3.13.05.i (462), 
2.5.01.03e (515), 2.5.05.02.i (565), 2.5.05.03b (570), 2.5.05.04 (572), 
2.6.06.01.i (637), 2.6.09.05a (644), C.2.6.09.03a (660), C.2.6.09.03b 
(661), C.2.6.09.09 (670), 2.7.04.03 (716), 3.3.00.01 (759), 
3.3.00.02a.i.c (762), 3.3.00.02a.i.d (763), 3.3.00.07d.iv.a (806), 
3.3.00.07d.iv.b (807), 3.3.00.07d.iv.c (808), 3.3.00.07d.v.a (809), 
3.3.00.07d.v.b (810), 3.3.00.07d.v.c (811), 3.3.00.10.i (815), 
3.3.00.10.ii (816), and E.3.9.06.00.04 (862).

VEGP Unit 4 ITAAC

    2.2.03.08c.xii (197), 2.5.05.02.i (565) and 2.5.05.03b (570).
    The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3 
combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP 
Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS 
Accession No. ML14100A135).

II. Licensee ITAAC Post-Closure Notifications (IPCNs)

    SNC has submitted an ITAAC IPCN under 10 CFR 52.99(c)(2), informing 
the NRC of new information that materially alters the basis for 
determining either that inspections, tests, or analyses was performed 
as required, or that acceptance criteria is met for:

VEGP Unit 3 ITAAC

    2.5.02.07a (534).

VEGP Unit 4 ITAAC

    Since the last Federal Register notice of the NRC staff's 
determinations of successful completion of inspections, tests, and 
analyses (86 FR 50381;

[[Page 5867]]

September 8, 2021), the NRC staff has not made additional 
determinations of the successful completion of inspections, tests, and 
analyses based on licensee IPCNs submitted under 10 CFR 52.99(c)(2).
    The ITAAC for VEGP Unit 3 are in Appendix C of the VEGP Unit 3 
combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP 
Unit 4 are in Appendix C of VEGP Unit 4 combined license (ADAMS 
Accession No. ML14100A135).

III. NRC Staff Determination of Completion of ITAAC

    The NRC staff has determined that the specified inspections, tests, 
and analyses have been successfully completed, and that the specified 
acceptance criteria are met. The documentation of the NRC staff's 
determination is in the ITAAC Closure Verification Evaluation Form 
(VEF) for each ITAAC. The VEF is a form that represents the NRC staff's 
structured process for reviewing ICNs and IPCNs.
    Each ICN presents a narrative description of how the ITAAC was 
completed. The NRC's ICN review process involves a determination on 
whether, among other things: (1) Each ICN provides sufficient 
information, including a summary of the methodology used to perform the 
ITAAC, to demonstrate that the inspections, tests, and analyses have 
been successfully completed; (2) each ICN provides sufficient 
information to demonstrate that the acceptance criteria of the ITAAC 
are met; and (3) any NRC inspections for the ITAAC have been completed 
and any ITAAC findings associated with that ITAAC have been closed. The 
NRC's review process for IPCNs is similar to that for ICNs but focuses 
on how the licensee addressed the new, material information giving rise 
to the IPCN.
    The NRC staff's determination of the successful completion of these 
ITAAC is based on information available at this time and is subject to 
the licensee's ability to maintain the condition that the acceptance 
criteria are met. If the NRC staff receives new information that 
suggests the NRC staff's determination on any of these ITAAC is 
incorrect, then the NRC staff will determine whether to reopen that 
ITAAC (including withdrawing the NRC staff's determination on that 
ITAAC). The NRC staff's determination will be used to support a 
subsequent finding, pursuant to 10 CFR 52.103(g), at the end of 
construction that all acceptance criteria in the combined license are 
met. The ITAAC closure process is not finalized for these ITAAC until 
the NRC makes an affirmative finding under 10 CFR 52.103(g). Any future 
updates to the status of these ITAAC can be found by selecting the link 
``ITAAC Status Report'' on the NRC's websites: https://www.nrc.gov/reactors/new-reactors/col-holder/vog3.html and https://www.nrc.gov/reactors/new-reactors/col-holder/vog4.html.
    This notice fulfills the NRC staff's obligations under 10 CFR 
52.99(e)(1) to publish a notice in the Federal Register of the NRC 
staff's determination of the successful completion of inspections, 
tests, and analyses.

Vogtle Electric Generating Plant Unit 3, Docket No. 5200025

    A complete list of the review status for VEGP Unit 3 ITAAC, 
including the submission date and ADAMS accession number for each ICN 
received, the ADAMS accession number for each VEF, and the ADAMS 
accession numbers for the inspection reports associated with these 
specific ITAAC can be found by selecting the link ``ITAAC Status 
Report'' at the NRC's website https://www.nrc.gov/reactors/new-reactors/col-holder/vog3.html.

Vogtle Electric Generating Plant Unit 4, Docket No. 5200026

    A complete list of the review status for VEGP Unit 4 ITAAC, 
including the submission date and ADAMS accession number for each ICN 
and IPCN received, the ADAMS accession number for each VEF, and the 
ADAMS accession numbers for the inspection reports associated with 
these specific ITAAC, can be found by selecting the link ``ITAAC Status 
Report'' at the NRC's website https://www.nrc.gov/reactors/new-reactors/col-holder/vog4.html.

    Dated: January 27, 2022.

    For the Nuclear Regulatory Commission.
Victor E. Hall,
Chief, Vogtle Project Office, Office of Nuclear Reactor Regulation.